Distribution facilities 

RTP Ajdovščina

Obnova 20kV stikališča v RTP/20 kV Ajdovščina

Contract was signed in

 2020 

Scope of work
  • Construction works
    • Supply of primary equipment for medium voltage equipment
    • Electrical installation works
    • Assmebly, supply, mounting and instalaltion of secondary equipment cases for high and medium voltage switchyards
    • Project documentation preparation
    • Assembly, supply, mounting and installation of control and protection system
    • Configuration and parametrization
    • FAT and SAT tests
    • Commissioning
Investor

Elektro Primorska d.d.; Erjavčeva ulica 22, 5000 Nova Gorica, Slovenija

 Renewal of 20 kV switchyard in Ajdovščina

With our partner, Kolektor Koling, we are currently in the implementation of the reconstruction phase of the 20 kV switchyard on a 110/20 kV distribution transformer substation in Ajdovščina. The reconstruction comprises the renewal of the building, new cable sewer, existing installations reconstruction and installation of new ones in the 20 kV extension, production and supply of secondary equipment for high and medium voltage switchyards.