Renewal and upgrade of distribution transformer substation in Slovenska Bistrica 

Implementation year

2019 

Scope of work

•Production, assembly, supply, mounting and installation of control and protection system
• Parametrization management
• FAT and SAT tests
• Commissioning

 

Investor

Elektro Maribor d.d.; Vetrinjska ulica 2, 2000 Maribor, Slovenija

 

 

 

Due to age of the equipment in the distribution transformer substation of Slovenska Bistrica which resulted in poor and unstable electricity supply, a need for renewal Due to age of the equipment in the distribution transformer substation of Slovenska Bistrica which resulted in poor and unstable electricity supply, a need for renewal of the substation grew. 110 kV air insulated switchyard was replaced by a new 110 kV GIS switchyard, which need less space and the weather conditions don't affect its operation.